Altheon S.R.L.S.

We develop plants for CER, PPAs and self-consumption and support those who build them.

An Italian development and advisory firm in renewables, based in Legnago (Verona). We structure plants for renewable energy communities (CER), power purchase agreements (PPAs) and self-consumption, and support those who hold land, energy demand or capital through to bankability. We do it on our own projects too.

What we do

From origination to operation, what we do and what we coordinate.

We follow projects from origination to commissioning: site scouting, permitting, coordination of the engineering and construction carried out by partners, structuring how the energy is sold. The diagram separates what we do from what we coordinate.

Who does what, phase by phase

Altheon carries out development and coordinates the partners who build and run the plant. It does not build with its own means, does not advance capital and does not take on the role of Referent (Soggetto Referente).

Roles along a plant's chain: for each phase, what Altheon, the delivery partners, the project owner and the providers of capital do.
Phase 1Origination and developmentPhase 2Permitting and grid connectionPhase 3ConstructionPhase 4Operation and monetisation
Altheon

Carries out

Site scouting, landowner agreements, yield and financial model, deal structure (PPA term sheet or CER structure).

Carries out

Permitting: documents, dealings with the authorities, timelines. Grid connection request through to the general minimum technical solution (STMG) from Terna or the distribution operator.

Coordinates

Detailed design, supply and construction entrusted to partners. Supports the project owner on EPC and supply contracts and in tracking time, cost and progress.

Coordinates

The operation and maintenance (O&M) provider: production data and contractual indicators. Supports the plant owner in selling the energy. Where there is a CER, sets up its allocation rules with partner lawyers.

Delivery partners

Legal and technical professionals, brought in when needed.

Licensed design firm: design, technical filings, grid studies.

Design firm: detailed design and site supervision (direzione lavori). EPC or general contractor: construction. Suppliers of modules, inverters and components.

O&M provider: operation and maintenance.

Owner and capital

Site owner: land or roof, under surface rights or a lease. Offtaker: the buyer of the energy.

Project owner: approves the design and the connection solution.

Project owner: signs the EPC and supply contracts. Investor and lender: the capital to build.

Plant owner: sells the energy. Offtaker: buys it, for example under a PPA. Investor and lender: periodic reporting. Where there is a CER, the Referent (Soggetto Referente), the GSE's contractual counterparty.

  1. Phase 1Origination and development

    Altheon

    Carries out

    Site scouting, landowner agreements, yield and financial model, deal structure (PPA term sheet or CER structure).

    Delivery partners
    Legal and technical professionals, brought in when needed.
    Owner and capital
    Site owner: land or roof, under surface rights or a lease. Offtaker: the buyer of the energy.
  2. Phase 2Permitting and grid connection

    Altheon

    Carries out

    Permitting: documents, dealings with the authorities, timelines. Grid connection request through to the general minimum technical solution (STMG) from Terna or the distribution operator.

    Delivery partners
    Licensed design firm: design, technical filings, grid studies.
    Owner and capital
    Project owner: approves the design and the connection solution.
  3. Phase 3Construction

    Altheon

    Coordinates

    Detailed design, supply and construction entrusted to partners. Supports the project owner on EPC and supply contracts and in tracking time, cost and progress.

    Delivery partners
    Design firm: detailed design and site supervision (direzione lavori). EPC or general contractor: construction. Suppliers of modules, inverters and components.
    Owner and capital
    Project owner: signs the EPC and supply contracts. Investor and lender: the capital to build.
  4. Phase 4Operation and monetisation

    Altheon

    Coordinates

    The operation and maintenance (O&M) provider: production data and contractual indicators. Supports the plant owner in selling the energy. Where there is a CER, sets up its allocation rules with partner lawyers.

    Delivery partners
    O&M provider: operation and maintenance.
    Owner and capital
    Plant owner: sells the energy. Offtaker: buys it, for example under a PPA. Investor and lender: periodic reporting. Where there is a CER, the Referent (Soggetto Referente), the GSE's contractual counterparty.
  • Carries out: work done by Altheon
  • Coordinates: work done by partners, coordinated by Altheon
Text description

The map reads by columns, from the first phase to the last, and by rows, one lane per party: Altheon, the delivery partners, the project owner and the providers of capital.

In Altheon's lane a line runs across the four phases. It is solid, with filled nodes, in phases 1 and 2, where Altheon carries out the work; it is dashed, with hollow nodes, in phases 3 and 4, where Altheon coordinates work done by partners. At each phase a thread drops from the line to the node in the delivery partners' lane.

The table gives, phase by phase and lane by lane, the same information as the drawing.

Method

How we work.

Four steps, from the first message to the engagement.

  1. First contact

    Write through the form or by email and set out the context: a site, an energy need, a stalled project, an operating plant. We reply within two business days.

  2. The call

    If the topic fits, a 30-minute call is enough to understand the context and whether working together makes sense.

  3. The proposal

    If the conditions are there, a working hypothesis for the deal structure or the scope of work: what to do and in which order. If we are not the right fit, we say so.

  4. The engagement

    We carry out the agreed activities and bring in the partners each discipline needs.

Projects

Recent work.

Anonymised summaries of advisory and due diligence engagements. We publish little, and only after clearance.

Selected engagement · CER architecture

Anchoring a CER around a continuous industrial load

Designing the governance, tariff model and monitoring stack for a Comunità Energetica anchored by a manufacturing plant operating on a three-shift cycle.

Selected engagement · Investor DD

Acquisition-side diligence on a utility-scale PV portfolio

Consolidated technical, regulatory and O&M diligence across a multi-site PV portfolio, supporting an institutional buyer’s final bid and closing conditions.

Tools

Two software products, for project data and for CERs.

Early access

AIP Engine. Structured due diligence on project data.

AIP Engine reads data rooms (PDFs, spreadsheets, scans) and produces a structured dossier, the Dossier Digitale Strutturato (DDS): a machine-readable view that investors, lenders and asset managers can analyse and compare across projects.

Built for our acquisition-side due diligence work. Now in early access for investors and asset managers active in Italian solar.

Launch phase

CER-Ops. Software for the monthly cycle of a CER.

Member registry, hourly meter-data import, recalculation of shared energy and of the premium tariff (TIP), allocation across members, one PDF statement each.

Built by Altheon for those who run a CER, it is a separate product with its own site, cerops.altheon.it. It is in its launch phase, with invitation-only access.

Resources

The rules in three figures, with their sources.

Three values set by the rules and tariffs in force for energy communities, each with its source. The rest is in the resources: frequently asked questions, glossary, indicative calculator.

20 years

Duration of the premium tariff on shared energy, from the plant's commercial operation date.

Source: Italian Ministry of Environment and Energy Security (MASE), MASE Ministerial Decree no. 414 of 7 December 2023 (CACER Decree), signed text, art. 1(2) and art. 4(1), (3) and (7). Verified on 2 October 2026.

The tariff applies until the thirtieth day after 5 GW of incentivised capacity is reached, and in any case no later than 31 December 2027.

1 MW

Maximum capacity of a single plant, or upgrade, to access the premium tariff.

Source: Italian Ministry of Environment and Energy Security (MASE), MASE Ministerial Decree no. 414 of 7 December 2023 (CACER Decree), signed text, art. 3(2)(a). Verified on 2 October 2026.

11.90 €/MWh

Unit fee of the valorisation contribution on self-consumed energy in a CER: the variable part of the low-voltage transmission tariff.Year 2026

Sources

Get in touch

Have land, an offtake or a stalled project?

Write to Michele. We reply within two business days.